Projects
Explore our comprehensive portfolio showcasing our footprint across the agriculture, industrial, transportation, energy and infrastructure sectors. Each project reflects our steadfast dedication to engineering excellence, transparent contract management and timely execution. By adhering to the highest international standards, we transform complex visions into sustainable, enduring assets that build the future.
Almaty / Kazakhstan
Project Description: The Almaty Ring Road has been implemented as a 20-years BOT (Build-Operate-Transfer) where the concessionaire is responsible for design, building, financing, operating, collecting tolls and maintaining the road.
The Almaty Ring Road is a 66 km long asphalt paved road located in the northern part of Almaty. The road has been constructed as Category I-a and 13,5 km is 2×2, 52,5 km is 3×2. The main road is connected to the existing traffic network via 55 km 2 lanes asphalt paved roads within 7 interchange locations. To serve the operation period, an Intelligent Traffic Management and Toll Collection System as well as Maintenance Yard has been constructed.
The design and construction has been completed in 50 months. The Almaty Ring Road has 21 bridges and 19 viaducts and other elevated structures. Design speed is 150 km/h.
Bucharest / Romania
The main objective is the design and execution of the works for Bucharest Ring Road km 0 + 000 – km 100 + 900: – Lot 1: Sector 1. Km 52 + 070 – Km 52 + 770 for North Belt and Sector 2. Km 52 + 770 – Km 69 + 000 for South Belt.
The total length of this Lot is 16,93 km with 2×2 lanes. The geometric elements of the route were designed for the speed of 120-140 km/h.
Bucharest / Romania
The main objective is the design and execution of the works for Bucharest Ring Road km 0 + 000 – km 100 + 900: – Lot 1: Sector 1. Km 52 + 070 – Km 52 + 770 for North Belt and Sector 2. Km 52 + 770 – Km 69 + 000 for South Belt.
The total length of this Lot is 16,93 km with 2×2 lanes. The geometric elements of the route were designed for the speed of 120-140 km/h.
Antalya / Türkiye
The Project consists of the engineering, procurement and construction of 11,1 km long light railway system with 16 stations, 8 transformer substations, 1 depot-maintenance area and a depot connection line. The supply of 14 vehicles is also in the scope of the project.
Istanbul / Türkiye
The turn-key project consists of the engineering, procurement and construction of 3,7 km long metro system between Sishane and Yenikapi with 3 stations. The supply of 92 vehicles and full integration into an existing metro system is also included in the scope of the project.
Ankara / Türkiye
The turn-key project consists of the engineering, procurement and installation of the railway line between Istanbul and Ankara, total 206 km, in order to achieve the train speed up to 200 km/h.
The work includes design and construction of the electrification, signalization and telecommunication systems, infrastructure and superstructure of Esenköy – Inonu Section and the disassembly of the existing line. The curb radiuses will be enlarged and new viaducts, tunnels and level crossings will be constructed.
İstanbul / Türkiye
The project consists of detailed design and construction of the M2 main line section from 4.Levent Station trail line until the end of Hacıosman Station, Sanayi, İTÜ Ayazağa, Atatürk Oto Sanayi, Darüşşafaka, Hacıosman stations, Seyrantepe Depot Area connection Lines and Seyrantepe Depot Area, Workshop and Station Building and Super structure Works as well as provision, assembly and commissioning works of the electro-mechanical systems.
Samsun / Türkiye
The turn-key Project consists of the construction works, mechanical installation works, electrical installation works, electromechanical works, vehicle supplying and commissioning works, design and engineering works and infrastructural works, as well spare parts and vehicle special equipments for the rail system consisting of 2.0 km single track between Üniversite and Körfez, 15.2 km double tracks between Körfez and Cumhuriyet, with 21 stations and transformer structures, one depot area and a depot connection track.
Pavlodar / Kazakhstan
The Project consisted of the engineering, procurement and execution of all civil, mechanical and electrical and instrumentation works of the Copper Concentrator on turn-key basis. The Concentrator included a steel structured manufacturing hall with a total closed area of 90 thousand m² and additional buildings with a total closed area of 40 thousand m².
Main quantities of project;
• 16,000 ton equipment,
• 3,000 ton piping,
• 1,700 ton tank,
• 900 km cabling,
• 15,000 ton structural steel and
• 100,000 m³ concrete.
Adana / Türkiye
The Karakuz Dam and Hydroelectric Power Plant Project is located on the Körkün River within the boundaries of the Pozantı and Karaisalı Counties of the Adana Province. The annual energy production of the plant with an installed capacity of 76 MW is 276 GWh. The project consists of intake and outlet structures as well as derivation and energy tunnels, coffer-dams, access roads on either side of the lake, balance tank, penstock, power plant, switchyard and transmission lines.
The dam consists of a concrete body with a crest length of approximately 200 m and a height of 45 m from the foundation. The dam lake area is 29,9 hm² with a total volume of 5.112 hm³ and the access road around the lake is 6,2 km. The 321 m long derivation tunnel has a diameter of 6 m and the 11 km energy tunnel (Two TBMs (Tunnel Boring Machine) were used for the energy tunnel) has an interior diameter of 3,1 m. There are two Pelton type turbins in the power plant. The 154 kV switchyard was connected to the National Power Distribution System by a 32 km long energy transmission line.
Kırklareli / Türkiye
The annual energy production of the plant with an installed capacity of 81.99 MW is 594.000.000 kWh. The plant is Combined Cycle Power Plant and consists of two (2) P&W FT.8 SWIFTPACK combustion turbines rated at 30 MW gross each and one (1) condensing steam turbine generator rated at 22 MW gross at annual mean ambient site conditions
Astana / Kazakhstan
The project consists of detailed engineering, procurement and implementation of all civil, mechanical, electrical and instrumentation works on a turn-key basis. Design and construction of a water treatment system (capacity 100,000 m³/day), a water intake structure in a pond with 23 m diameter (capacity 210,000 m³/day), water network distribution line (150 km) and rehabilitation of 17 sewage intermediate pump stations.
Türkiye
The Project which is mainly based on the engineering works for a pipeline system will be installed at approximately 250 m below the sea surface and tethered to the seabed (max. depth 1,400 m) and spanning 80 kms of sea crossing originates at Anamur (Turkey) and terminates at Güzelyalı (Cyprus). The pipeline will be formed as a single line HDPE-100 pipe as in the diameter of 1,600 mm and provide 75 million m3/year water and it will be the first project which will be constructed as in such length.
Çankırı / Türkiye
In 2024, with the goal of expanding into the international market, Turkey’s first and Europe’s largest hybrid microgranule fertilizer factory was established in the Çankırı Yakınkent Organized Industrial Zone. With an annual production capacity of 12,000 tons and a closed area of 8,300 m², the Palmira Agro factory stands out in the sector in terms of both production efficiency and environmental sustainability with its 1,200 kWp capacity solar energy system.
Through their positive impact on early-stage plant development, microgranular fertilizers allow producers to achieve higher yields with lower input levels. This approach supports long-term agricultural sustainability while promoting more efficient use of natural resources.
Shymkent / Kazakhstan
Construction of Greenhouse Complex in Kazakhstan including design works, earthworks, greenhouse structures, greenhouse surrounding roads, administrative and service buildings, infrastructure and landscaping works, gas and energy supply works. Project Area – 1,695,555 m² Closed Area – 1,216,000 m² (Steel Structure) Main / Auxiliary Buildings: 2,020 m² Earthworks – 4,800,000 m3 Road Works – 2 Lanes – 39,068 m² (5,046 m) Asphalt Road
Eskişehir / Türkiye
Construction of Greenhouse Complex in Eskişehir including design works, earthworks, greenhouse structures, greenhouse surrounding roads, administrative and service buildings, infrastructure and landscaping works, gas and energy supply works. The Eskişehir Mahmudiye Modern Greenhouse Project is planned to be Europe’s largest modern soilless greenhouse operating under a single roof in terms of production area. Project Area – 950,820 m² Closed Area – 812,608 m² (Steel Structure)
Istanbul / Türkiye
The Project consists of the engineering, procurement, construction, assembly and system integration, testing & commissioning works of 22.5 km long mass transit rail system between Kabataş-Mecidiyeköy-Mahmutbey with 6.5 km TBM/NATM tunnel construction work and viaducts, whole construction works of 3 stations, Architectural and electromechanical works of 15 stations, 1.5 km depot yard connection line and superstructure of the depot area and maintenance buildings.
Bucharest / Romania
The turn-key project consists of engineering, procurement, construction of 6,3 km double tube TBM tunnel, 6 stations, 1 integration station and 8 ventilation shafts. The project completion phase has 9 months of design, 39 months of execution and 60 months of defect liability period.
This project is the first phase of a metro line that will connect Bucharest city center with Henri Coanda International Airport. With the completion of the project, 50 thousand passengers will be transported in one direction and the existing metro network will be connected to the International Airport.
Konya / Türkiye
Alarko Food Industry’s innovative production facility, which became operational in Konya Ereğli in 2025, will be drying 14 types of fruit, 31 types of vegetable and cheese derivatives, offering them for direct consumption and use in the food industry. The facility has a cooling capacity of 60,000 m3/h and an installed electrical transformer power of 1600 kVA.
50,000 m² Project Area
12,500 m² Factory Building
300 m² Auxiliary Facilities Building